| 1. Product Scope and Traceability |
| Product classification | GB/T 11981; ASTM C645; EN 14195 | The product must be identified as a non-load-bearing metal framing component intended for gypsum plasterboard or ceiling systems. Structural studs must not be substituted without engineering approval. | Product datasheet, section drawing, declared application, production code, and packaging photographs. | Non-load-bearing ceiling stud; galvanized cold-formed steel section. | Verify |
| Batch traceability | Quality-control requirement supporting all three standards | Every shipment should be traceable to a coil number, production date, material grade, coating designation, and inspection record. | Mill certificate, coil traceability list, batch inspection report, and carton or bundle labels. | One coil number linked to each production batch and packing list. | Verify |
| 2. Steel Material and Mechanical Properties |
| Base-metal thickness | GB/T 11981; ASTM C645; EN 14195 | Confirm base-metal thickness separately from zinc coating. For an ASTM C645 nonstructural member, a commonly specified minimum base-metal thickness is 0.455 mm, equivalent to approximately 0.018 in; the contract and applicable edition govern. | Calibrated micrometer records taken after coating removal or a clearly defined base-metal measurement method; third-party inspection report. | 0.50 mm base metal, with a stated manufacturing tolerance. | Verify |
| Steel grade and yield strength | GB/T 11981; EN 14195; project specification | The supplier must declare the steel grade and mechanical properties. The selected grade must be suitable for the specified span, load, screw pull-out, and deflection requirements. | Original mill certificate showing grade, yield strength, tensile strength, elongation, heat number, and test standard. | Cold-rolled galvanized steel; nominal yield strength declared as 350 MPa. | Verify |
| Material uniformity | GB/T 11981; ASTM C645; EN 14195 | Steel strip should be free from cracks, laminations, excessive edge damage, and coating defects that could affect forming or corrosion resistance. | Incoming-coil inspection procedure, surface photographs, nonconformance records, and sampling plan. | Visual inspection at coil entry and after roll forming. | Verify |
| 3. Profile Dimensions and Manufacturing Tolerances |
| Nominal section width | GB/T 11981; EN 14195; approved shop drawing | Section width must match the ceiling grid, perimeter track, clips, connectors, and board system. Nominal dimensions must be stated in millimetres. | Controlled section drawing with tolerances, first-article inspection report, and calibrated dimensional records. | 50 mm, 75 mm, or 100 mm nominal stud width, selected according to the approved system. | Verify |
| Flange and lip dimensions | GB/T 11981; EN 14195; approved shop drawing | Flange width, return lip, and edge geometry must be consistent enough to maintain board screw clearance and reliable engagement with the track. | Profile drawing, go/no-go gauge records, and sample cross-section measurements. | Typical flange: 35–50 mm; typical return lip: 6–15 mm, subject to the approved profile. | Verify |
| Length and cut accuracy | GB/T 11981; EN 14195; purchase specification | Cut lengths must fit the installation schedule without excessive site cutting. Ends should be square, clean, and free from dangerous burrs. | Cut-length inspection report, bundle label, production order, and random shipment measurements. | Standard lengths: 2,400 mm, 3,000 mm, or project-defined lengths. | Verify |
| Profile straightness and twist | GB/T 11981; EN 14195; project specification | Members must remain sufficiently straight and stable for level ceiling installation. Any numerical limit must be taken from the applicable standard or approved project specification. | Straightness and twist inspection method, inspection table, calibrated tools, and recorded sampling results. | 100% visual screening plus documented sample measurements per production batch. | Verify |
| 4. Corrosion Protection and Surface Condition |
| Zinc or metallic coating designation | GB/T 11981; ASTM C645; EN 14195 | A corrosion-resistant metallic coating must be declared and appropriate for the exposure environment. The coating mass or thickness must not be presented as a standard compliance claim unless supported by the applicable edition. | Coating certificate, coating designation, gravimetric or magnetic-thickness test report, and coating supplier declaration. | Z120 galvanized coating designation, meaning 120 g/m² total coating mass on both surfaces when specified under the relevant coating system. | Verify |
| Coating continuity and adhesion | ASTM C645; EN 14195; GB/T 11981 | Coating should be continuous and sufficiently adherent for roll forming, cutting, fastening, and normal indoor installation. Red rust, peeling, and exposed unprotected areas are unacceptable. | Surface inspection report, coating adhesion or bend-test records where applicable, and photographs of formed sections. | No visible red rust, peeling, flaking, or coating delamination on sampled pieces. | Required |
| Cut-edge protection | Project specification; corrosion-control requirements | Cut edges should be clean and free from excessive burrs. If the installation environment requires enhanced protection, the supplier must state the approved edge-treatment method. | Deburring procedure, edge-treatment declaration, and installation instructions. | Clean roll-formed edges; no additional coating unless required by the approved system. | Verify |
| 5. Standard-Specific Compliance Documentation |
| GB/T 11981 compliance file | GB/T 11981, applicable edition | Chinese-market products should be evaluated against the applicable version of GB/T 11981 for dimensions, appearance, material, coating, and mechanical requirements relevant to the product category. | Chinese test report from a competent laboratory, product standard declaration, inspection rules, and batch release records. | Report identifies the exact profile, thickness, material grade, coating, test date, and batch. | Verify |
| ASTM C645 compliance file | ASTM C645, applicable edition | Confirm that the member is nonstructural framing and that base-metal thickness, corrosion resistance, dimensions, and workmanship meet the specified edition and project requirements. | ASTM-referenced test report, base-metal thickness results, coating documentation, dimensional report, and product identification. | Report references the exact ASTM C645 edition used for evaluation. | Verify |
| EN 14195 compliance file | EN 14195, applicable edition | For European projects, confirm the product designation, declared performance, factory production control, and any construction-product regulatory documentation required for the destination market. | Declaration of Performance where legally applicable, CE-related documentation where applicable, factory production-control records, and test reports. | Documentation identifies the metal framing component and its intended gypsum-board system use. | Verify |
| 6. Factory Capability and Quality Assurance |
| Roll-forming capability | Supplier quality requirement | The production line should control strip alignment, roll gap, profile geometry, punching, cutting, and automatic length measurement. | Factory audit, equipment list, process flow chart, maintenance records, and sample production video or inspection visit. | In-line roll forming with automatic cut-to-length control and profile gauges. | Verify |
| Calibration system | Quality-management requirement | Thickness gauges, micrometers, calipers, coating instruments, scales, and other inspection devices must have valid calibration status. | Calibration certificates traceable to a recognized national or international measurement system. | Calibration records current within the defined inspection interval. | Verify |
| Sampling and release inspection | GB/T 11981; ASTM C645; EN 14195; purchase specification | Each production batch should be released only after checks of thickness, profile dimensions, length, appearance, coating, and marking. | Inspection and test plan, batch release certificate, control charts, nonconformance procedure, and corrective-action records. | Inspection frequency defined by batch size and risk level; results retained for the contract period. | Verify |
| 7. Packaging, Delivery, and Pre-Shipment Verification |
| Packaging and moisture control | Project specification; corrosion-control requirement | Bundles must be protected from rain, condensation, salt contamination, impact, and deformation during inland transport and export shipping. | Packaging specification, loading photographs, moisture-control plan, and container inspection checklist. | Strapped bundles on level supports with protective wrapping and ventilation provisions. | Verify |
| Product marking | GB/T 11981; EN 14195; project specification | Markings should allow the profile, size, thickness, coating, length, batch, and production date to be identified after delivery. | Label artwork, bundle photographs, packing list, and traceability records. | Each bundle marked with profile, dimensions, thickness, length, quantity, batch, and production date. | Required |
| Independent pre-shipment inspection | Contract quality plan | For large or critical orders, an independent inspection should verify sampled dimensions, base-metal thickness, coating, quantity, packaging, and documentation before shipment. | Signed inspection report, sampling plan, photographs, nonconformance disposition, and retained samples. | Inspection completed before container sealing; unresolved deviations remain open. | Recommended |
| 8. Supplier Selection Decision Rules |
| Technical compliance | GB/T 11981; ASTM C645; EN 14195 | Do not approve a supplier when the exact standard edition, profile, thickness, coating, or test method is missing from the submitted documents. | Completed compliance matrix with document numbers, issue dates, laboratory details, and product-batch references. | All mandatory rows supported by current, product-specific evidence. | Pass only if complete |
| Sample approval before mass production | Project quality plan | Approve a physical sample only after checking fit with the track, connectors, suspension components, screws, and gypsum board used in the project. | Signed sample approval sheet, dimensional photographs, installation trial record, and approved reference sample. | One approved sample retained by both purchaser and supplier. | Required |
| Final supplier rating | Purchaser evaluation procedure | Recommended approval threshold: no critical nonconformities; all standard-specific documents available; technical score at least 90%. | Completed supplier scorecard covering compliance, factory control, delivery, packaging, communication, and corrective-action performance. | Technical score: 90% or higher; critical deviations: 0. | Set by buyer |