| Technical compliance and design fit | 15% | Rated voltage, transformer capacity, frequency, protection, enclosure rating, operating environment, and applicable local standards. | Require a clause-by-clause compliance schedule, single-line diagram, equipment list, and clearly documented exceptions. |
| Engineering and commissioning support | 15% | Availability of design reviews, installation guidance, commissioning assistance, troubleshooting, and escalation contacts. | Confirm the named support roles, service hours, response-time commitments, site-support rates, and commissioning scope in writing. |
| Delivery schedule and logistics | 15% | Design approval, manufacturing, factory testing, shipping, site delivery, and installation milestones. | Compare a dated project schedule showing lead time from approved drawings, shipping assumptions, delivery responsibilities, and schedule contingencies. |
| Quality assurance and testing | 10% | Document control, inspection points, component traceability, factory acceptance testing, and test-record handover. | Request the inspection and test plan, sample test reports, factory acceptance test procedure, and defect-resolution process. |
| Warranty and remedies | 10% | Warranty duration, start date, covered components, exclusions, repair or replacement process, and travel or labor coverage. | Compare the actual contract terms; check whether coverage begins at delivery, commissioning, or another defined milestone. |
| Spare parts and long-term serviceability | 5% | Availability of critical spares, recommended stock, replacement-component compatibility, and service documentation. | Request a critical-spares list with indicative availability, pricing validity, and expected support arrangements over the planned service life. |
| Initial purchase and installation cost | 10% | Equipment price, engineering, testing, transport, unloading, installation interfaces, and commissioning charges. | Compare like-for-like scope and identify exclusions, optional items, taxes, currency assumptions, and site-work responsibilities. |
| Energy losses and operating cost | 8% | Transformer no-load and load losses, expected loading profile, energy price, and operating hours. | Use guaranteed loss figures and a common load profile. Estimate annual loss cost as annual loss energy (kWh) × electricity price per kWh. |
| Routine maintenance requirements | 5% | Inspection frequency, maintenance tasks, consumables, required shutdowns, and specialist labor needs. | Ask for the maintenance schedule, estimated labor hours, consumables list, and any special tools or training requirements. |
| End-of-life and replacement considerations | 7% | Disassembly access, material documentation, fluid handling where applicable, and removal or recycling responsibilities. | Clarify decommissioning scope, disposal obligations, and available material or equipment documentation; do not assume resale or salvage value. |