| 1 | Compare total landed cost, not just the machine price | List the machine, included equipment, export packing, freight, insurance, import charges, inland delivery, installation, and initial spares. | Use the cost worksheet below. Request separate line items and confirm which costs are included in the seller’s quotation. |
| 2 | Match rated capacity to your actual production target | Specify required output in tonnes per day and operating hours per day. Ask whether the rating refers to maize input or finished flour output. | Request a process-flow description and a written capacity guarantee for the maize and product specification you intend to use. Actual output depends on configuration and operating conditions. |
| 3 | Define flour quality and product yield | Agree on the required particle size, extraction rate, bran separation, and product moisture specifications. Confirm how results will be measured. | Include a sample test or acceptance criteria in the purchase contract; “high quality” alone is not a measurable specification. |
| 4 | Check cleaning and food-contact provisions | Confirm the proposed cleaning stages, such as screening, aspiration, or destoning where required. Ask for material details for product-contact parts and a cleaning procedure. | Compare the complete process line rather than assuming that a mill alone includes grain cleaning, conveying, or flour packing equipment. |
| 5 | Confirm electrical and site requirements | Match motor voltage, frequency, phase, and total connected load to the site supply. Check starting current, cable requirements, floor loading, and required clearances. | Obtain motor nameplates and a layout drawing before ordering. Price any electrical upgrades, foundations, or utility work separately. |
| 6 | Plan shipping around packed dimensions and Incoterms | Request packing dimensions, gross weight, number of packages, lifting points, and loading plan. Confirm the named delivery place and Incoterms® rule in the quotation. | Get a freight quote using the actual cargo details. Clarify who arranges export clearance, main carriage, insurance, import clearance, and final delivery. |
| 7 | Budget installation and commissioning separately | Confirm whether installation supervision, travel, accommodation, commissioning, operator training, and start-up testing are included. | Request a written scope and schedule. Identify work that must be completed by the buyer, such as foundations, wiring, lifting equipment, or local labor. |
| 8 | Price critical spare parts before purchase | Ask for part numbers, recommended stock quantities, prices, and dispatch lead times for wear parts such as screens, belts, bearings, and grinding components, as applicable to the design. | Build an initial spare-parts package around expected operating hours and local replenishment times. Verify that manuals identify parts clearly. |
| 9 | Review documentation, warranty, and support terms | Check for operating and maintenance manuals, wiring diagrams, parts lists, warranty duration, exclusions, and the process for technical support. | Get warranty and support commitments in writing, including how faults are reported and who pays for replacement-part transport. |
| 10 | Set measurable pre-shipment and acceptance tests | Agree on test material, run duration, throughput, product specifications, included components, and how any shortfall will be handled. | Use a signed test report and a clear acceptance procedure. Align payment milestones with inspection and agreed delivery documents. |